|

April 28,
2006 |
New
neighbors: Emerson Place construction project progresses
For passersby walking along Blossom Street in front of the MGH Gray and
Jackson buildings, the large construction project at Emerson Place has
become a curious display. Construction crews are hard at work building
two 12-story residential towers, one 16-story residential tower, three
townhouses and three stories of an underground parking garage as part
of a comprehensive development project managed by a company called Equity
Residential.
While the construction project began in January with the demolition of
existing structures, the project now is entering a new phase that will
be even more noticeable for the MGH community. During the next couple
of weeks, the construction crews will begin blasting procedures to remove
rock ledges to make way for the underground garage. The MGH has been working
closely with the general contractor
and environmental consultants hired by Equity Residential to ensure a
safe environment is maintained during the entire project and particularly
during the blasting phase of construction. Right,
an artist's rendering of the new building
"Equity Residential and its contractors reached out to us from the
very beginning to make sure the MGH property that abuts this construction
project remains safe, and hospital operations continue uninterrupted,"
says George MacNeil, Administrative Assets manager for MGH Buildings and
Grounds. "They've put monitoring equipment and sensors in key areas
such as the Operating Rooms and Radiation Oncology to make sure the construction
doesn't result in disruptive vibrations that could interfere with procedures
or sensitive equipment. We've been very pleased with the collaborative
spirit of this project with our new neighbors."
The blasting activity that will commence soon is highly regulated by the
Boston Police and Fire departments as well as the City of Boston. The
blasting is engineered and controlled with safety measures taken throughout
the process to ensure minimal disruption to the areas surrounding the
construction. Staff members from Buildings and Grounds, the MGH Environmental
Health and Safety Office and MGH Police and Security have convened a network
of MGH staff from various departments to monitor the effects of the blasting
should any occur and quickly notify the construction contractor of any
problems.
The blasting phase of the project — which will last for three months
— will begin with test blasts that will be completed during the
first two or three days of activity. Audible pre- and post-blast alerts
are required for each test and actual blasting event. These alerts will
consist of three loud, short air-horn bursts five minutes before the blast,
two air-horn bursts one minute before the blast and one air-horn burst
at completion. The tentative plan is to have a blasting session in the
morning and another in the afternoon.
In addition, MGH staff have been working with the contractors to ensure
traffic is properly controlled during construction; parking is still accessible
and safe; deliveries to the hospital are still made without obstruction;
dirt and debris are controlled properly; and The Clubs at Charles River
Park remain open and accessible. For more information or for questions
about the construction project, contact George MacNeil at (617) 726-2411
or Bob Castaldo, director of the MGH Environmental Health and Safety Office,
at (617) 726-2425.
|